FAT of the electric propulsion motor for the 3rd Barracuda submarine
Wednesday, February 03 2016
The first functional testing observation of the electric propulsion motor for the 3rd Barracuda submarine took place at ECA Group’s premises mid-December 2015.
Thanks to this observation, it has been able to monitor that the unit tests of the two motors and the four cabinets were progressing well.
This milestone has been validated by two representatives of DCNS Indret (West of France), thus enabling packing and storage of this equipment.
The general tests are scheduled as of June 2017 for an expected delivery in September 2017 at DCNS Indret.